Rebuilding the Square Meter: Planking

Today we started the planking process.
The boat is hanging which helps with access.
The existing planking is sound.
First off was an inspection of the existing planking.  Below the waterline the planking is either sound or absent.  Near the shear, there are a few planks that have rot near butt joints.  These will be dealt with later when we are in refinishing mode.  The planking we will be working on now is over the new framing we put in.  Here are some photos with descriptions...

Here you can see the new framing and the new planking going in.

Here is a close-up.  The planks are cut to fit, forced into place.  We then drill a pilot and a countersink.
After all the planks are fitted and screwed in, they will be removed and reset with thickened epoxy.
This might happen Friday when the weather will be warmer.

Here is an interior view of the same planking.

Ditto
The tails are long and will be cut to shape later.